Welcome to the Wolcott, VT, United Methodist Church. Unfortunately, due to the uptick in covid-19 cases during the past few weeks, we have decided to suspend live worship once again. Worship will continue to be available via zoom every week, however, and the link can be found here on the front page of the website every Sunday morning. The service is also posted so that you can follow along and participate if you wish. Following the service, Pastor's Mike's sermon will be posted, as well. We welcome you to join us on Sunday mornings whether or not you are a regular part of our congregation.
4023 VT Route 15
, Wolcott
, VT
05680
Map & Directions →
802.888.0395
posted on April 19
UPDATE: Phase Seven of our Historic Restoration Project is nearing completion. During the week of April 12, most of the clapboarding was completed with the exception of the far panel on both the east and the west side. Needed repair under the eaves and the remaining clapboards will be completed during the coming week. Phase Seven included removing the old clapboards at the top of the building on the east and west sides and the front, blowing insulation into the walls and covering with tyvek, and replacing the old clapboards with new pre-primed spruce clapboards. The estimate for this phase of the project is $26,300 and we still need to raise about $5,000. If you would like to help, you can send a check the WUMC, PO Box 94, Wolcott, VT 05680 or go to the "Giving" Tab on this website. We greatly appreciate all of the support which we have received for this very special project over the past 3 three years.
Phase Six of our Historic Restoration Project was completed in the late fall of 2020. Phase Six involved removing the clapboards on the front and side corners of the exterior of the building so that the front wall and sides can be insulated about 8 feet up. Currently, there is little to no insulation in the front or side walls so that the hallway is very cold and we have experienced freezing pipes in the bathroom during the past two winters. Once the wall is insulated it will be covered with new clapboards. We hope that this will be the next-to-last phase before completion of the painting of the exterior and repair of the outer walls under the eaves which we will hope to complete during 2021.
Phase Five of our Historic Restoration Project has now been completed . Our kitchen cabinets, sink, and countertops have been installed. Over the winter we insulated the outside walls of the fellowship hall and sheetrocked and painted the walls a light cream color which will make the entire hall much lighter and more inviting. The front hall has been repainted and the finishing touches have been put on the kitchen and the fellowship hall. Once we can open the church to the public once again, it is our plan to open up use of these rooms to anyone in the community who needs a place for meetings, events such as birthday parties, baby or wedding showers, or whatever is needed.
Phase Four - closing in the front wall of the Fellowship Hall, adding a wider, handicapped accessible door and painting the floor in the Hall so that we can once again use the hall for events-is now nearly completed with the exception of some finish work. We held our first event in a year-and-a half when we hosted racism training for clergy and laity from the Vermont District.
We have now completed Phase Three of our Historic Restoration Project. We would like to thank everyone who has contributed to our Restoration Project to date. As a result of your support we have a new handicapped accessible entrance ramp and have been able to completely repair the back wall so that we will have no more worries re: water infiltration into the foundation. There is still a need to finish the entrance, floor, and kitchen and we will be working on that in the months to come. We could not have come this far without your support and are praying that you will continue to support us as move forward to Phase Four - completing the front interior wall of the fellowship hall along with enlarging the doorway as well as painting the floor. Once this is done, we will have use of the hall once again.
Week 26 saw the completion on our handicapped bathroom! We now have a fully functional bathroom once again - much larger and more pleasant than our previous one.
Week 23 ended with more plumbing work being completed on our handicapped bathroom. An additional wall needed to be added to accommodate the required grab bars, so we will now also have a small closet in the bathroom, as well. And the door also needed to be moved. We have received a number of donations in memory of Linda Clark, who died very unexpectedly on August 6 and who was one of our most active members and an avid supporter of the historic restoration project.
Week 18 of our historic restoration project saw work beginning on our handicapped bathroom. The framing of the room has been completed. We now need to choose flooring for the bathroom before we can move forward. It is our current goal to be able to install the bathroom prior to winter. We are presently about $6,000 short of having enough funds to meet this goal.
Week 17 saw the pouring of the concrete slab, completing Phase One. Our next step is to finish raising funds for our handicapped bathroom. Many thanks again for all of you who have supported our Historic Restoration Project.
posted on April 18